Hardened Network Army Stages 1 & 2
$66 million - Baulderstone
Earthworks, Service Installations and Pavements
-
This project comprised of two separate stages with Bardavcol engaged as a major subcontractor to Baulderstone undertaking preparatory earthworks for building pads, building precinct road pavements, communications and high voltage trenching, retention basins, open drains, stormwater and miscellaneous civil works.
-
Construction of heavy duty pavements including reinforced concrete pavements.
-
Installation of spread footing foundations and earth retaining structures such as rock protection and guide banks for retention basins.
-
Complex service relocation including high voltage and communication conduits to Department of Defence Standards.
-
Coordinating works with Defence personnel including complex stakeholder interface works.