Torrens Rail Junction
$35 million - Connexion Alliance (Laing O'Rourke / DIT / AECOM / KBR)
Bulk earhworks, stormwater drainage road and rail infrastructure
-
Enabling works including access tracks and pads to cater for 100+ tonne piling rigs along both sides of the new 1.5km rail cutting.
-
Excavation of a 120,000 cubic metre rail cutting for the Outer Harbour Railway Line under the Gawler and ARTC lines and Park Terrace.
-
Extensive stormwater drainage including jacked pipes under rail (with a 10m deep jacking pit) as well as 3km of HDPE track drainage.
-
Placement of 1.5km of new rail formation, capping and ballast for the dual-carriageway Outer Harbor line.
-
New pavements, lighting and traffic controls at Park Terrace